Program:

To convert a former volunteer fire department to a full time,
full service facility. The
new second story addition included new sleeping quarters,
day, kitchen, toilet rooms, showers and exercise room. This
required constructing a new floor system above the existing
roof deck system. This upper floor contains all the private,
in house functions.
The first
floor program included an education room, ADA accessible upgrades,
new equipment room and workshop areas. The former squad bays
were converted to new administrative offices. A new entrance
canopy was added to the structure.
Date
Completed:

1994
Owner:

City of Twinsburg, Ohio
Contractor:

Whitehouse Construction
Cost:

$750,000
5,000 SF new construction
5,000 SF renovation |